A weep hole required, at handover
The wrong stage to be finding it.
In short: A weep hole recorded as required at practical completion in Austral.
What a weep hole does
It drains the cavity. Water through the outer brick skin runs down, lands on a flashing and leaves through the weep hole. Remove any part of that and the water stays in the wall.
What was recorded
Weep hole required, at high severity, on an Austral practical completion inspection, together with a control joint not continuous on the same job.
Why handover is too late
At lock-up this is a bricklayer and a chisel. At handover the brickwork is finished, sometimes rendered, and correcting it means cutting into completed work.
How builders respond
They resist, for the reason above. The counter is a report that cites what the detail fails rather than describing how it looks, and a dated photograph.
The lesson for your build
Book lock-up. Every envelope item on this page belongs there, and every one of them was found months later.